Project update Vestmanna: Electricity production during load test interrupted
GOTHENBURG, Sweden, June 12, 2023 /PRNewswire/ -- Minesto, leading ocean energy developer, has for ten days carried out a load test during electricity production with a new potentially performance-enhancing subsystem. Yesterday the production was interrupted, and an unplanned surface recovery was successfully carried out.
During the summer, Minesto carries out a series of load tests with new system configurations to increase and secure the Dragon 4 system performance and robustness when exposed to high loads at maximal tidal stream velocities. On Sunday, an unplanned surface recovery was carried out in collaboration with Minesto's local installation partner.
"Unplanned production stops are unwanted but a natural consequence of the load tests we carry out to verify and push the load limits at maximized production. The Dragon 4 is now undergoing analysis, service and preparations for re-installation," said Dr Martin Edlund, CEO of Minesto.
For additional information, please contact
Cecilia Sernhage, Chief Communications Officer
+46 735 23 71 58
ir@minesto.com
The following files are available for download:
Press release |
Share this article